{*}
Add news
March 2010 April 2010 May 2010 June 2010 July 2010
August 2010
September 2010 October 2010 November 2010 December 2010 January 2011 February 2011 March 2011 April 2011 May 2011 June 2011 July 2011 August 2011 September 2011 October 2011 November 2011 December 2011 January 2012 February 2012 March 2012 April 2012 May 2012 June 2012 July 2012 August 2012 September 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 October 2013 November 2013 December 2013 January 2014 February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 December 2018 January 2019 February 2019 March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026 February 2026 March 2026 April 2026
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
19
20
21
22
23
24
25
26
27
28
29
30
News Every Day |

Former Disy leader questions rising costs of Paphos-Polis road

Former Disy leader Averof Neophytou on Saturday expressed bemusement at the rising costs of construction for the new road which, if completed, will link Paphos with Polis Chrysochous, with the latest tender for the road’s construction drawing bids which will cost the taxpayer almost twice the originally forecast budget.

Neophytou is uniquely placed to comment on the matter, having previously served both as public works minister and as the mayor of Polis Chrysochous, and wrote in a post on social media that he had warned the government back in 2024 against terminating public works contracts with the aim of driving down costs.

“With the government’s justification that it dares to terminate them in order to finish them faster and cheaper for the taxpayer, I had pointed out that exactly the opposite will happen,” he said.

Thus far, discussions in earnest have only taken place regarding the first phase of the project, which will connect the village of Ayia Marinouda, just outside Paphos, and the village of Stroumbi, which is located roughly halfway between the road’s two endpoints – a distance of around 15.5 kilometres.

Initially, the government had signed a contract with Greek construction firm Intrakat – now known as Aktor – in 2021, aiming to have the first phase complete by the start of 2025.

However, that contract was torn up in 2024, with the public works department later lamenting that Intrakat’s “demand for additional costs and time to complete the project” were deemed to be “extremely problematic and excessive”.

Of this, Neophytou said on Saturday that “the reason for the termination, according to the government, was the contractor’s reasonable demands for an additional €25 million”, with the original contract, signed in 2021, having been worth €73m plus value added tax.

If the additional €25m had been granted, the road would have been finished by now at a cost of €98m,” he said, before pointing out that “after almost two years of delays, the bids were reopened, and the lowest bid is €125m”.

He pointed out that the government had already paid €16m to Intrakat for the work on the road it had performed so far, meaning that the total cost of the project will now cost €141m.

Averof Neophytou

“If the bid is awarded in the end, without counting any extras which will arise during the execution of the project, [there will be] a total cost of €141m,” he said.

He said that compared to the total cost of €98m which Intrakat had requested, “in the end, the project will cost us an additional €43m”.

“And, as I predicted then, it will not be finished during the term of the current government,” which expires in February 2028.

Two new bids for the completion of the road have been submitted so far, with one having been submitted by under-fire construction company Cyfield, worth just shy of €125m.

The other bid was jointly submitted by the Cypriot subsidiary of Lebanese firm Araco and Bulgarian construction company Geostroy, and is worth almost €129m.

Both of these bids are far higher than the amount estimated by the public works department when it put the project back out to tender last summer, with the department at the time saying that the road would cost a total of €90.2m plus VAT.

On this matter, it said that the tearing up of the original contract and increases in the cost of construction materials in recent years had led to the estimate rising from the originally forecast €73m.

As well as Intrakat’s demands for more money, the department had last year decried a “long delay in the execution of the project” and a “very slow pace of work” during the time in which Intrakat held the rights to construct the road.

It added that “in essence, from April 2024, work stopped being carried out other than excavations in a small section”, thus leaving “no other option than to terminate the contract”.

Additionally, it said that Intrakat’s final request for more funds had amounted to a request for €34m extra, which would have brought the total cost of the project to €107m, and an extension of almost five years on the project’s completion deadline.

“Considering that these demands were made with the project only 21.1 per cent complete, it can be reasonably concluded that there would be additional demands and extensions before the project was complete,” it said.

Ria.city






Read also

French right divided over primary vote one year from presidential election

Si la guerra ha terminado, ¿cuándo volverá todo a la normalidad?

Cubs closer, WBC hero Daniel Palencia lands on IL in team’s latest injury nightmare

News, articles, comments, with a minute-by-minute update, now on Today24.pro

Today24.pro — latest news 24/7. You can add your news instantly now — here




Sports today


Новости тенниса


Спорт в России и мире


All sports news today





Sports in Russia today


Новости России


Russian.city



Губернаторы России









Путин в России и мире







Персональные новости
Russian.city





Friends of Today24

Музыкальные новости

Персональные новости