{*}
Add news
March 2010 April 2010 May 2010 June 2010 July 2010
August 2010
September 2010 October 2010 November 2010 December 2010 January 2011 February 2011 March 2011 April 2011 May 2011 June 2011 July 2011 August 2011 September 2011 October 2011 November 2011 December 2011 January 2012 February 2012 March 2012 April 2012 May 2012 June 2012 July 2012 August 2012 September 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 October 2013 November 2013 December 2013 January 2014 February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 December 2018 January 2019 February 2019 March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026 February 2026 March 2026 April 2026
1 2 3 4 5 6 7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
News Every Day |

From Shipyards Comes Seapower: Revitalizing Naval Shipbuilding

Introduction

Since the fall of the Iron Curtain, the U.S. Navy’s acquisition of new ships maintains a troubling pattern. Reforms based upon accountability, design before production, and a reformation of the naval shipyard workforce will lay the groundwork for a resurgence in naval shipbuilding.  The Zumwalt class destroyers, designed to fulfill the concept of the 21st Century Destroyer, were truncated after per ship costs increased by more than 80 percent over initial projections. The Italian FREMM Constellation-class frigate has suffered delays and cost growth due to U.S. Navy design requirements, raising concerns that it may resemble previous acquisition failures. The FFG(X) program may also rely on legacy U.S. Coast Guard cutters for certain missions. However, these vessels cannot mount vertical launch system (VLS) cells, limiting their air-defense and strike capabilities.       

The History of American Shipbuilding Struggles 

Brian Potter’s analysis in “Why Can’t the U.S. Build Ships?” outlines the historical struggles of American shipbuilding, which is crucial in understanding how historical trends paved the way for current issues. The start of World War I revealed an ugly truth to the American shipping industry. The reliance on foreign ships for international trade quickly faded away when hostilities opened, as foreign nations recalled and requisitioned their own ships for their war efforts. The Shipping Act of 1916 birthed the U.S. Merchant Marine Fleet, resulting in the U.S. accounting for around 20% of all the world’s shipping after the end of the Great War. The arrival of the Great Depression forced many shipyards to close, crippling the ability to produce ships prior to the start of World War II. The outbreak of the war was essentially a repeat of the Great War, with the U.S. once again hard-pressed to revive a shipbuilding industry for a total war. The construction of over 2,700 liberty ships was a testament to the quickness and scale at which America amassed ships during the conflict, and by the war’s conclusion, America possessed nearly 60% of total tonnage in the entire world.

American shipbuilding dithered for decades during the Cold War. Japan overtook both the United States and Britain as the largest shipbuilding industry in the world, and infrastructure developments through highway systems and railroads continued to eat away at the efficiency of commercial shipping within domestic movements. The Oil Crisis in the 1970s dried up demand for new ships that were built through the Merchant Marine Act of 1970. The Act brought in money to modernize shipyards as well as multiple Japanese shipbuilding firms to bring training and techniques to American companies. However, American companies had extreme difficulty adopting the Japanese practices, and efficiency was not at the levels that Japanese advisors expected it to be.

In the modern day, shipbuilding is defined by two circumstances: high cost of labor and steel as compared to foreign countries, and a production culture optimized for low-volume construction rather than serial efficiency. Compared to countries like Korea or Japan, American labor costs and steel costs are extremely high (approximately      four to six times greater than Asian industries), making American shipbuilding industries extremely unattractive due to higher costs for production. Due to this, the U.S. accounts for only 0.1% of global commercial shipping tonnage today. In regards to culture, a single crucial factor reinforces the stagnation in American shipbuilding. The Jones Act insulates U.S. shipbuilders from foreign competition, ensuring only American vessels are used for domestic shipping. This in turn ensures American shipbuilding does not constantly evolve in order to deal with international competition, as the commercial base is shielded from foreign competition through the act.

Current Issues With U.S. Navy Shipbuilding 

With a clear explanation of the historic struggles of commercial and naval shipbuilding, a groundwork of the current issues facing U.S. Navy ship programs can be explained in depth. A glaring fault is a systemic breakdown in the acquisitions process of shipbuilding. Over the past three decades, designs have been implemented before they had matured, constantly shifting requirements were seen as the norm, and in-production changes drove up costs. The Government Accountability Office (GAO) reviews prove that major ships enter the construction phase without achieving stable and complete functional design prior, a practice inconsistent with shipbuilding standards. 

In 2025, the GAO released a report with concern regarding the Constellation-class frigate, “In May 2024, we found that the Navy and the shipbuilder for the Constellation-class frigate program were struggling to stabilize the ship design and, consequently, ship construction had effectively stalled. These problems contributed to an estimated delay of 3 years…expecting to exceed the contract ceiling price.” The delay of the FREMM frigates has been exacerbated due to U.S. Navy specific design requirements, making procurement exponentially more expensive and slower. 

The GAO also reports that, “In October 2024, the Navy reported 759 metric tons of weight growth from initial estimates—nearly a 13 percent increase—due in part to the underestimation of applying Navy technical requirements to a foreign ship design.” The exposure of the issues plaguing the construction of the Constellation-class highlight the vicious cycle of acquisitions: unexpected cost growth, delivery delays measured in years due to design changes, and platforms delivered late and under planned build numbers. These overruns persist despite budgets, indicating that increased funding has not led to increased capability. The Navy has placed itself in a position where ships are built like prototypes, and not as part of a stabilized line of production.

Role of the Jones Act in Naval Shipbuilding

The Jones Act has zero impact on U.S. Navy shipbuilding, but it plays an indirect role in regards to the decline of naval shipbuilding. Commercial shipbuilding is not inclined to develop export competitiveness and block production practices, as they are shielded from foreign competition. Since a majority of these shipping companies are also contracted to produce naval shipping, these gaps transfer when building navy ships. Korea and Japan have proved that to build warships efficiently, a country has to build commercial ships efficiently first. Another critical issue of American shipbuilding culture that specifically affects U.S. warship production is the low production numbers. Navy shipyards that build destroyers can typically be contracted to complete 1-2 ships per year, and coupled with frequent design modifications, peak efficiency is rarely achieved by the shipyard. Compared to Japan or Korea, where shipyards rely on block production of standardized hulls, efficiency can be achieved due to the absence of modifications. U.S. shipbuilding emphasizes single designs with limited acceptability for error, while Asian shipyards prioritize standardized production that favors speed, cost control, and replaceability. Repeal of the Jones Act would force the industries to scale production to become competitive internationally, indirectly improving naval shipbuilding. Colion Grabow in War on the Rocks describes how the Jones Act unintentionally affects national security, “Perhaps more important than this relative disparity is the country’s inability to build new Navy ships and maintain existing ones. Decades of uncompetitive shipbuilding have degraded the industrial base to the point where there isn’t sufficient shipyard capacity to meet U.S. national security needs.” 

Reversing decades of failure in shipbuilding requires more than process reform or increased funding.

The following three pillars outline a reasonable plan: enforce accountability, design before construction, and a domestic workforce. 

Pillar 1: Accountability

The most pervasive issue facing naval acquisitions is the absence of accountability when programs predictably fail. Over the last 20 years, the shipbuilding budget has doubled in size, but the production and efficiency of shipbuilding have not matched a vastly increased budget. However, in FY2023, the Navy delivered only 7 of 13 ships required to maintain its annual requirement as dictated by planned force structure objectives. The Government Accountability Office (GAO) analyses attribute this failure to cost overruns, changes in design during building phases, and immature program baselines.

Addressing accountability in shipbuilding requires structural reforms that directly align outcomes of production to leadership authorities. Senior acquisition officials must be required to personally certify designs, cost projections, and requirement stability, with such certifications carrying profound legal significance. By linking these approvals to program performance, the acquisition system would introduce meaningful career consequences for knowingly approving unrealistic plans. In addition, cost and schedule overruns should automatically trigger an independent investigation through an Inspector General, placing a greater emphasis on the importance of accurately reporting changes in a program throughout its cycle. It is crucial to ensure that accountability enforcement can delineate between unintentional friction and deliberate fraud or waste. 

Pillar 2: Design Before Construction

The second pillar of reformation is the enforcement of a design-complete policy. U.S. naval ship programs routinely begin construction with unstable designs, guaranteeing costly rework and delays. Commercial shipbuilders and successful foreign naval producers treat design maturity as a prerequisite for ship production. Instituting a requirement for a complete certification of a design prior to steel being cut would save the American taxpayer remarkable amounts of money. 

This concept would require a deliberate separation of prototype from production in navy shipbuilding practices. The GAO states, “Attaining design stability helps assure that a product will meet cost and schedule targets, and programs that entered construction without stable designs did experience cost growth.” Once a design for a ship is frozen, production must start without significant changes to the original plan. As shown by numerous GAO reports, modifications during construction have driven up costs and delayed delivery of lines. Waivers to modify during production should be a rare occurrence, independently reviewed, and carry career consequences for approving officials, which will enforce personal accountability. Without strict design control, no workforce or funding on this planet can overcome the pains of design modifications during production. 

Pillar 3: National Shipbuilding Corps 

The third pillar is a revitalization of the domestic shipyard workforce. A GAO report regarding domestic shipyards states, “The Navy’s shipbuilding plans have consistently reflected a larger increase in the fleet than the industrial base has achieved…The shipbuilders have infrastructure and workforce challenges that have made the Navy’s goals difficult to accomplish.” This is largely what resulted in the Navy delivering only 7 of 13 vessels in FY 2023, leaving the force under operational capacity. CRS testimony also states, “Workforce challenges appear to be a central factor in projected delays and capacity constraints. These challenges include difficulties in recruiting and retaining sufficient numbers of production workers at shipyards and supplier firms…and limited numbers of ship designers.” The workforce present in the United States simply is not enough to keep up with the demands of naval shipbuilding, and civilian industries offer more lucrative opportunities for workers. America has suffered the loss of industry and jobs, crushing our ever-shrinking blue collar workforce for far too long. To revitalize our shipyards, our nation must incentivize work through career pipelines, recruitment drives, and educational programs. 

The creation of a Naval Shipbuilding Corps that emulates the spirit of the Civilian Conservation Corps would provide a mechanism to grow the domestic shipbuilding workforce. The NSC would only recruit U.S. citizens, with its primary demographics as young adults and dispossessed workers, and place them into service contracts that come with the structure of paid employment, official trade training, and apprenticeships feeding directly into local shipyards. Workers would be pipelined into skills such as welding, electric work, quality checks, and naval architecture work as aligned with Navy certification benchmarks. Training pipelines would center around local community colleges, trade schools, maritime colleges, and union apprenticeships, ensuring that worker skills transfer seamlessly between civilian and government sectors. 

NSC personnel would be allocated to shipyards facing the greatest workforce shortages. Federal funding would cover initial labor costs to reduce any risk for employers while onboarding the initial workforce. Unlike a majority of hiring, the NSC would have planned manpower flows that are directly related to Navy shipbuilding schedules. This empowers shipyards to scale production and personnel as needed. The NSC would include benefits such as wages matching commercial positions, making this employment competitive to civilian alternatives. Governance and maintenance of the NSC would be jointly led by both the Department of the Navy and the Department of Labor, ensuring that acquisitions and workforces are aligned under both “chains of command” needed to execute proper shipbuilding. By making a national workforce that feeds into shipyards, the NSC would dutifully address the labor issues identified by the GAO in numerous reports. 

Conclusion

Naval power has always depended on the ability to build, outnumber, repair, and replace ships faster than one’s adversary.

The heart of the U.S. Navy’s power projection depends upon the ability to efficiently produce quality ships in order to align with the goals of the National Defense Strategy and fleet modernization goals. The historical trends of American shipbuilding show that despite periods of decline and struggle, our industry is able to be revitalized in times of conflict. Three crucial solutions that can improve shipbuilding are enforced accountability, complete designs prior to production, and the creation of a National Shipbuilding Corps. If the United States intends to deter conflict in the First Island Chain, shipbuilding must become a national effort, and not another GAO report that is disregarded months after its publication.

The post From Shipyards Comes Seapower: Revitalizing Naval Shipbuilding appeared first on Small Wars Journal by Arizona State University.

Ria.city






Read also

Executing with Prejudice: Israel’s Death Penalty Law

The Feeling of Becoming Less and Less of a Person

2 bedroom Apartments for sale in Nueva Andalucía – R5330431

News, articles, comments, with a minute-by-minute update, now on Today24.pro

Today24.pro — latest news 24/7. You can add your news instantly now — here




Sports today


Новости тенниса


Спорт в России и мире


All sports news today





Sports in Russia today


Новости России


Russian.city



Губернаторы России









Путин в России и мире







Персональные новости
Russian.city





Friends of Today24

Музыкальные новости

Персональные новости