{*}
Add news
March 2010 April 2010 May 2010 June 2010 July 2010
August 2010
September 2010 October 2010 November 2010 December 2010 January 2011 February 2011 March 2011 April 2011 May 2011 June 2011 July 2011 August 2011 September 2011 October 2011 November 2011 December 2011 January 2012 February 2012 March 2012 April 2012 May 2012 June 2012 July 2012 August 2012 September 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 October 2013 November 2013 December 2013 January 2014 February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 December 2018 January 2019 February 2019 March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026 February 2026 March 2026
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
22
23
24
25
26
27
28
29
30
31
News Every Day |

A Vital US Navy Warship Is Nearly Back in Service—After a 10-Year Wait

The USS Tortuga might be better known if she had not spent the last decade undergoing maintenance—a far longer span of time than her initial construction! 

The USS Tortuga (LSD-46) isn’t as high-profile a warship as the US Navy’s nuclear-powered supercarriers, and it isn’t as well-armed as the Arleigh Burke-class guided-missile destroyers. However, the Whidbey Island-class dock landing ship was designed to transport and launch landing craft, vehicles, and Marines in expeditionary operations. Such a warship could prove vital in a conflict in the Indo-Pacific.

The problem for the Navy is that LSD-46 has been undergoing a nearly decade-long refit, keeping the ship out of service for even longer than it originally took to build her.

Last Friday, the US Navy shared an image of USS Tortuga departing from Naval Station Norfolk to begin sea trials.

“It was the first time the Whidbey Island-class dock landing ship has gotten underway since 2014,” the Navy said. “Tortuga is in the final stages of a year-long modernization project contracted by BAE Systems, managed by Mid-Atlantic Regional Maintenance Center. The sea trials will test the ship’s enhancements, upgrades, and vital engineering and combat systems as the crew certifies the ship ready for operations.”

It is unclear how long the sea trials—which will evaluate the propulsion, navigation, communication, and combat systems—will take. Still, final certification of LSD-46 depends on the successful completion of the tests.

About the USS Tortuga Dock Landing Ship

  • Year Commissioned: 1990
  • Length: 610 ft (186 m)
  • Beam: 84 ft (25.6 m)
  • Draft: 21 ft (6.4 m)
  • Displacement (Full Load): ~15,939 – 16,839 tons
  • Propulsion: Four Colt Industries 16-cylinder diesel engines, 2 shafts (33,000 shp)
  • Speed: 20+ knots (23 mph, 37 km/h)
  • Armament:
    • One MK 31 Mod 0 RAM Launchers
    • Two MK 15 MOD 2 Close-in-Weapons Systems (CIWS)
    • Two MK 38 MOD 2 25mm Machine Gun Systems
    • Six .50 Cal machine guns
    • Well Deck: Four LCAC (Landing Craft, Air Cushioned) or 21 LCM-6 landing craft
    • Flight Deck: 2 helicopter pads
  • Crew: ~400+ (approx. 20 officers, 25 CPO, 302 enlisted), plus passengers

LSD-46 is the sixth Whidbey Island-class dock landing ship. The vessel was laid down in March 1987 at Avondale Shipyards in New Orleans, and, due to the threat of Hurricane Gilbert, she was launched earlier than expected in September 1988. The ship suffered no reported damage in that storm and was commissioned in November 1990.

Why Is the Tortuga’s Refit Taking So Long?

Many jokes have been made about the Russian Navy’s efforts to modernize its warships—notably its “flagship” aircraft carrier, the Admiral Kuznetsov, which the Kremlin reportedly gave up on in July 2025. Still, the fact remains that the US Navy has also faced numerous hurdles in keeping its fleet’s maintenance on schedule.

The refit of the nuclear-powered Nimitz-class supercarrier USS George Washington (CVN-73) was delayed for years during its midlife refueling, resulting in horrible conditions for the sailors. At issue is the lack of facilities to service and maintain the fleet, as well as the US Navy’s continuing shift in priorities.

BAE Systems was awarded a $139.8 million contract back in 2017 for just 16 months of the “restorative work,” which was completed at the company’s shipyard in Norfolk. The extended modernization was driven by unexpected repair needs, which created significant integration challenges.

The Government Accountability Office (GAO) warned in a late 2019 report that the initial timeline was already insufficient, due to labor and material shortages and planning inefficiencies. The matter was made worse by the global COVID-19 pandemic in early 2020 and the supply chain challenges that followed.

However, the US Navy never gave up on the ship.

“[LSD-46’s] return comes as the Navy continues to manage an aging amphibious fleet. Many vessels are staying in service longer than originally planned, making modernization programs increasingly important,” Interesting Engineering wrote.

About the Author: Peter Suciu

Peter Suciu has contributed to dozens of newspapers, magazines and websites over a 30-year career in journalism. He regularly writes about military hardware, firearms history, cybersecurity, politics, and international affairs. Peter is also a contributing writer for Forbes and Clearance Jobs. He is based in Michigan. You can follow him on Twitter: @PeterSuciu. You can email the author: Editor@nationalinterest.org.

The post A Vital US Navy Warship Is Nearly Back in Service—After a 10-Year Wait appeared first on The National Interest.

Ria.city






Read also

The president of Colombia has just been labeled a “priority target” for his alleged drug ties by the DEA

As Supreme Court hears issue, poll shows 80% want to return to Election DAY

Chuck Norris, macho star of ‘Walker, Texas Ranger’, dies at 86

News, articles, comments, with a minute-by-minute update, now on Today24.pro

Today24.pro — latest news 24/7. You can add your news instantly now — here




Sports today


Новости тенниса


Спорт в России и мире


All sports news today





Sports in Russia today


Новости России


Russian.city



Губернаторы России









Путин в России и мире







Персональные новости
Russian.city





Friends of Today24

Музыкальные новости

Персональные новости