Add news
March 2010 April 2010 May 2010 June 2010 July 2010
August 2010
September 2010 October 2010 November 2010 December 2010 January 2011 February 2011 March 2011 April 2011 May 2011 June 2011 July 2011 August 2011 September 2011 October 2011 November 2011 December 2011 January 2012 February 2012 March 2012 April 2012 May 2012 June 2012 July 2012 August 2012 September 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 October 2013 November 2013 December 2013 January 2014 February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 December 2018 January 2019 February 2019 March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
21
22
23
24
25
26
27
28
29
30
31
News Every Day |

Southern Marin flood control projects inch forward

Marin flood control officials have approved $1.8 million for a half-dozen infrastructure projects in Mill Valley, Tamalpais Valley and Marin City.

The projects, approved by the Flood Zone 3 Advisory Board on Jan. 13 for its next two-year budget cycle, range from pumps to levees. The funds will pay for pre-construction planning and engineering for systems that minimize high tides and upland runoff, according to staff and consultant reports.

“We’re making progress,” said Garry Lion, board chair. “It’s kind of slow and painful, but we’re making progress getting things into their proper allocation budgets.”

For Mill Valley, the panel approved $700,000 to complete the engineering to replace the Sycamore pump station, which handles stormwater runoff. The station predates the district and is run by the Mill Valley Department of Public Works. Last year, the city awarded a $4.2 million contract for its replacement.

Two other projects concern tidal waters in the Tamalpais Junction area. The board approved $250,000 to hire real estate consultants to report on acquiring rights of way as a precursor to replacing the Cardinal Road levee with a “sheet-pile wall,” a staff report said.

“This proposed project will address seepage through the concrete wall and earthen levee from Flamingo Road to about 1,100 feet downstream along the left bank of Coyote Creek,” another county report said. The flood district estimated the levee mitigation would cost $4.2 million.

An additional $50,000 will be spent to survey sediment levels and stream banks along Coyote Creek, Nyhan Creek and Bothin Marsh, the report said. Lion said a bike path is near these lowlands that stretch inland from the northern end of Richardson Bay.

Another $60,000 will be spent to bring the Crest Marin pump station up to code and stabilize the bank of Nyhan Creek “around the outfall,” a staff report said. The district’s consultants estimated the pump station replacement would cost $5.9 million.

The final project on the flood district budget concerned one of several pending projects in Marin City. Two years ago, the district installed a temporary pump system at the wetland pond along the Highway 101 exit and Drake Avenue. The site is the only vehicle access to the neighborhood and it floods in king tides.

The pump worked during the king tides early this month, but high bay waters immediately across the highway flooded areas of northern Sausalito. The flood district approved $704,000 to prepare construction plans for a permanent pump station. Of that sum, $125,000 will be spent to automate turning on the temporary pump.

The flood district is also coordinating with state and federal agencies that are planning other flood and stormwater projects at the entrance to Marin City. Caltrans has proposed fixing an aging drainage culvert that connects the wetland pond to Richardson Bay and building a new culvert under Highway 101 to drain into Richardson Bay.

Last summer, county flood and water officials received numerous comments from Sausalito residents in floating homes at Gate 6 1/2 Road, which lies across from the wetland pond. They were concerned increasing drainage flows would negatively affect the bay bottom below their homes.

Several residents raised those concerns at the Flood Zone 3 board meeting. Lion said planners are looking at moving the proposed new culvert slightly to the north.

The flood district is also studying draining and dredging the wetland pond, which has “elevated lead and zinc, typical of freeway runoff, as well as elevated arsenic due to natural geology,” a staff report said. It noted the state has allocated $2.5 million for environmental dredging.

Terrie Green, chair of the Marin City Community Services District board, has repeatedly called on Caltrans to mitigate runoff from Highway 101 above Golden Gate Village, the county’s largest public housing project, that flows downhill into the wetland pond.

The flood district budget estimated the “total future costs” of its Marin City pond projects at $4.1 million. The estimated costs for the Marin City projects, the Cardinal Road levee mitigation and the Crest Marin pump station approach $14 million.

The district has a $19 million fund balance, a staff report said.

Lion said the district would move forward with construction when the final engineering and permitting are completed, and as more funds become available.

Ria.city






Read also

America SOARs at Night

NYT Pips hints, answers for January 20, 2026

Western Carolina visits Okojie and Mercer

News, articles, comments, with a minute-by-minute update, now on Today24.pro

Today24.pro — latest news 24/7. You can add your news instantly now — here




Sports today


Новости тенниса


Спорт в России и мире


All sports news today





Sports in Russia today


Новости России


Russian.city



Губернаторы России









Путин в России и мире







Персональные новости
Russian.city





Friends of Today24

Музыкальные новости

Персональные новости