Add news
March 2010 April 2010 May 2010 June 2010 July 2010
August 2010
September 2010 October 2010 November 2010 December 2010 January 2011 February 2011 March 2011 April 2011 May 2011 June 2011 July 2011 August 2011 September 2011 October 2011 November 2011 December 2011 January 2012 February 2012 March 2012 April 2012 May 2012 June 2012 July 2012 August 2012 September 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 October 2013 November 2013 December 2013 January 2014 February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 December 2018 January 2019 February 2019 March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
News Every Day |

Highway 37 bridge project in Novato gets $25M influx

A plan to raise a bridge in a flood-prone area of Highway 37 in Marin County is in line for a $25 million funding boost.

The Transportation Authority of Marin is set to transfer the funds to the California Department of Transportation for the Novato Creek Bridge replacement project. The funds are part of the county’s share of Regional Measure 3 bridge toll revenue administered by the Metropolitan Transportation Commission.

“What’s exciting about the new Novato Creek Bridge is that it’s going to be the first component of the entire 21-mile Highway 37 corridor that is constructed at the ultimate height,” said Marin County Supervisor Eric Lucan, whose District 5 includes Novato. “We’re going to see that segment right here in Marin, in an area that has experienced a lot of flooding and forced closures. We’re looking forward to it.”

Lucan is chair of the Transportation Authority of Marin board and a Marin representative on the State Route 37 policy committee. He said the TAM board is expected to approve the allocation at its meeting on Jan. 22. The allocation request would be submitted to the Metropolitan Transportation Commission for approval.

The plan to overhaul Highway 37 is a massive project, broken into several components, including some interim solutions. Ultimately, Caltrans will need to raise the entire road, an undertaking that is years away and expected to cost billions of dollars.

Caltrans is set to begin with the Novato Creek Bridge given its flooding problems, which have caused full highway closures since 2017 and headaches for tens of thousands of commuters. The bridge replacement is the first phase of a project to address flooding in the area of Highway 37 from Highway 101 to Atherton Avenue.

Phase one, at a cost of $270 million, involves constructing a new 26-foot-high bridge that can accommodate projected 2130 sea levels. The existing bridge deck is approximately 9 feet.

“The project is in the final stages of design, which will complete by the end of spring,” said Geoffrey Johnson, a Caltrans spokesperson.

Johnson said the Transportation Authority of Marin is a core partner in the effort to make the highway resilient to rising water. He said the $25 million allocation will support the addition of a 14-foot-wide multiuse path across the span.

“This path is a key feature that will enhance public access and safety for cyclists and pedestrians,” Johnson said.

Caltrans aims to begin construction in the spring of 2027 and finish in 2030.

The project is also supported by $155 million from the federal Infrastructure Investment and Jobs Act and $90 million in state funds.

The second phase, a $1.7 billion project, has yet to be funded. It would rebuild the remaining sections of the 2.5-mile portion of the highway as a 114-foot-wide, 35-foot-tall causeway, including a bicycle and pedestrian path.

“This first segment of the Highway 37 corridor plan has really been done well,” said U.S. Rep. Jared Huffman, a Democrat from San Rafael. “They’re elevating Highway 37; they have integrated SMART; there are going to be all kinds of multiple benefits.”

Huffman has been critical of Caltrans’ handling of other project components, including the three-phase, $500 million Sears Point-to-Mare Island project. That effort, an interim solution, will widen the highway to two lanes in each direction and fortify a portion of the San Pablo Baylands.

The project involves replacing the Tolay Creek Bridge, east of the Highway 37 and Highway 121 interchange, and extending an eastbound merge lane for a mile. The project also will restore a 3.5-mile section of degraded tidal salt marsh called Strip Marsh East to help protect against flooding while creating habitat.

Workers will install a tolled eastbound lane and widen the Sonoma Creek Bridge. Westbound improvements would be completed in a third phase.

The project is expected to withstand sea-level rise projections through 2050 and improve travel time and reliability. Construction is expected to begin in the fall and continue through winter 2030.

Huffman said the cost is too high for too little benefit.

“It’s going to be obsolete within 15 years of completion, and they’re going to add insult to injury by tolling everyone to drive on it,” Huffman said. “It’s really poorly conceived, unfortunately. And they’ve missed an opportunity to elevate it with a causeway that could open the door to the largest wetland restoration on the West Coast.”

Ria.city






Read also

Woman seen on video allegedly blocking Minnesota ICE operation with car as agitators surround agents

46 percent in new poll support abolishing ICE, 43 percent oppose

InterMaritime Shipmanagement appoints Erwin Derlagen as Senior Technical Director

News, articles, comments, with a minute-by-minute update, now on Today24.pro

Today24.pro — latest news 24/7. You can add your news instantly now — here




Sports today


Новости тенниса


Спорт в России и мире


All sports news today





Sports in Russia today


Новости России


Russian.city



Губернаторы России









Путин в России и мире







Персональные новости
Russian.city





Friends of Today24

Музыкальные новости

Персональные новости