Add news
March 2010 April 2010 May 2010 June 2010 July 2010
August 2010
September 2010 October 2010 November 2010 December 2010 January 2011 February 2011 March 2011 April 2011 May 2011 June 2011 July 2011 August 2011 September 2011 October 2011 November 2011 December 2011 January 2012 February 2012 March 2012 April 2012 May 2012 June 2012 July 2012 August 2012 September 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 October 2013 November 2013 December 2013 January 2014 February 2014 March 2014 April 2014 May 2014 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 December 2018 January 2019 February 2019 March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
27
28
29
30
31
News Every Day |

San Geronimo pipeline upgrade project approved

Seismically vulnerable segments of a pipeline that carries untreated water across the San Geronimo Creek are slated for replacement.

The board governing the Marin Municipal Water District unanimously approved the project on Dec. 16. The vote included the adoption of an environmental assessment that imposes steps to minimize potential disturbances to the creek and surrounding habitat.

The pipe is part of the district’s “North Marin Line,” which was constructed in 1957 to convey raw water from Kent Lake and Nicasio Reservoir to the San Geronimo treatment plant. Pipe crossings are supported by concrete trestles installed in the creek. The pipe is leaky and at the end of its useful life.

“It’s such a critical line in our system that we want to make sure that it’s operable, right?” said Elysha Irish, the district’s engineering manager. “Nicasio and Kent Lakes are some of our largest lakes in our system. Also, Soulajule (Reservoir) would be fed through that line should we choose to operate it.”

Irish said eventually the whole pipeline would need to be replaced as part of a larger project.

“These parts of the pipeline, they’re not underground, they’re not easily accessible, and just given the nature and complexity of these particular locations, staff wanted to repair these ahead of that larger project,” she said.

Ahead of the vote, board president Matt Samson thanked district staff for making progress on a project that has been delayed since 2016.

“This project was identified as a vulnerability for the district,” Samson said. “And we appreciate you continuing to bring it back up and reminding us of how important it is, and taking steps here to make sure our infrastructure is modernized so we can still meet the demands in the next 50 years on one of the most critical pipelines.”

Initially, the district planned to replace the pipes at the two points where they cross the creek. The pipe is the only transmission line from the reservoirs to the San Geronimo plant, the largest of the district’s three treatment plants.

The project was deferred for several years, and when it was evaluated more recently, district officials determined it would be best to relocate the connection from Kent Lake away from private roads and residences.

“The homes and trees and fences are very, very close to that existing pipeline, and it would be very difficult from a constructability standpoint to put a new bridge at that location,” Irish said.

The new plan involves installing about 1,700 feet of pipe under Sir Francis Drake Boulevard at Lower Peters Dam Road. The site is east of the Leo T. Cronin Fish Viewing Area in Samuel P. Taylor State Park. The pipe under Shafter Bridge would become part of the North Marin Line. A valve would also be relocated.

The changed scope prompted the district to perform a supplemental environmental assessment. The report reached a similar conclusion to one approved in 2016 that said all potential impacts could be mitigated to less than significant.

The 263-page report, officially called a supplemental initial study/mitigated negative declaration, was circulated for public review and comment in the fall.

The modified project also includes cutting and removing some of that pipe and the concrete pilings in the creek that support it. That would reduce the risk of potential debris buildup that could restrict flow and damage the pipe, officials said.

Plans to replace the pipe crossing the creek from Nicasio Reservoir remain unchanged from the original proposal. Once that old pipe is removed, a new 36-inch pipe would be installed onto a steel truss on piers. The pipe would be elevated about 2 to 3 feet above the ground before crossing the creek.

The creek would be dried out in the work area to provide safe access during the construction.

In response to public comments, district staff amended the design of the pipe so that it blends in better with the natural environment at points where it meets the ground.

Construction is expected to begin in August after the northern spotted owl nesting season. The estimated project cost is $3 million to $5 million.

Ria.city






Read also

Hooked on the claw: how crane games conquered Japan's arcades

Iran seizes an oil tanker in the Strait of Hormuz

Honduras joins the list of Latin American countries electing righ-wing leaders

News, articles, comments, with a minute-by-minute update, now on Today24.pro

Today24.pro — latest news 24/7. You can add your news instantly now — here




Sports today


Новости тенниса


Спорт в России и мире


All sports news today





Sports in Russia today


Новости России


Russian.city



Губернаторы России









Путин в России и мире







Персональные новости
Russian.city





Friends of Today24

Музыкальные новости

Персональные новости